June 2010
Fabrication and assembly of process modules and associated off-module pipespools and steelwork for the Devil Creek gas plant project was completed in June 2010 by head contractor Clough Ltd at their Sattahip fabrication yard and the modules shipped to the project site in North-western Australia. This followed an earlier shipment, consisting of the piperack modules, in February 2010. Detail design for the project was carried by Uhde's design office at Map Ta Phut, Thailand. Uhde and Clough cooperated in the development of a highly modular design concept for the process plant to optimise construction cost and schedule for the overall project.